City of Concord v. New Hampshire Water Supply & Pollution Control Commission

Supreme Court of New Hampshire

Decided July 31, 1975No. 7241PublishedCited by 1 opinion

1Per curiam

The city of Concord has pending an appeal under RSA 541:6 (Supp. 1974) from an order of the water supply *454and pollution control commission requiring the city to cover a water supply open distribution reservoir. After hearing, the commission on April 22, 1975, ordered the city to inform the commission not later than May 28, 1975, that it had adopted a program to cover the reservoir, appropriated funds for the program, and established a timetable for completing the improvements. A motion for rehearing was denied May 29, 1975, and the time for compliance with the order was changed to “forthwith”.

T…