This was an action for damages for breach of contract. The defendant appeals from a judgment for the plaintiff in the amount of $4,000.

On November 9, 1970, the plaintiff entered into a subcontract with the defendant whereby the plaintiff agreed to furnish labor, materials, and equipment and perform all carpentry work required to construct a service station and restaurant in Omaha, Nebraska. The contract provided the plaintiff would begin and terminate his work according to a “Critical Path Schedule” which was a detailed construction schedule set out in the contract. It provided the carpentry…

2Cases cited5 opinions

  1. Von Dorn v. MengedohtNebraska Supreme Court · 1894
  2. Ridenour v. KukerNebraska Supreme Court · 1970
  3. Hale v. George H. Hess & Co.Nebraska Supreme Court · 1890
  4. Roberts v. DrehmerNebraska Supreme Court · 1894
  5. Masten v. Campbell Manufacturing Co.Nebraska Supreme Court · 1972

3Cited by4 opinions

  1. Lamb Engineering & Construction Company v. Nebraska Public Power DistrictCourt of Appeals for the Eighth Circuit · 1997
  2. Siefford v. Housing Auth. of City of HumboldtNebraska Supreme Court · 1974
  3. Omaha Public Power District v. Darin & Armstrong, Inc.Nebraska Supreme Court · 1980