Cherry v. Charles Benson, Inc.
Appellate Court of Illinois
1Opinion of the CourtJustice Eldredge
On November 11, 1925, The Danville Hotel Company, as owner, and Charles Benson, Inc., as contractor, entered into a written contract for the construction of a hotel building for the sum of $604,899 in cash and $217,800 in common stock of the owner at the par value of $100 per share. For the faithful performance of this contract Charles Benson, Inc., as principal, and the Aetna Casualty & Surety Company (appellant) as surety, executed a bond in the penal sum of $822,699. This bond contained the following provision:
“Now, Therefore, the condition of this obligation is such that if the Principal…
2Cases cited39 opinions
- Knight & Jillson Co. v. CastleIndiana Supreme Court · 1909
- Getchell & Martin Lumber & Manufacturing Co. v. Peterson & SampsonSupreme Court of Iowa · 1904
- Byram Lumber & Supply Co. v. PageSupreme Court of Connecticut · 1929
- Fidelity Deposit Co. of Baltimore, Md. v. RainerSupreme Court of Alabama · 1929
- Baker & Co. v. BryanSupreme Court of Iowa · 1884
34 more not listed; retrieve them via the Exa API.
3Cited by9 opinions
- Cherry v. Aetna Casualty & Surety Co.Illinois Supreme Court · 1939
- Fodge v. Board of EducationAppellate Court of Illinois · 1941
- La Salle Iron Works, Inc. v. LargenSupreme Court of Missouri · 1966
- Maxwell ex rel. Maxwell v. NieftAppellate Court of Illinois · 1942
- People ex rel. National Cast Iron Pipe Co. v. MerkleAppellate Court of Illinois · 1933
4 more not listed; retrieve them via the Exa API.