Saturn Construction Co. v. Landis & Gyr Powers, Inc.

Appellate Division of the Supreme Court of the State of New York

Decided April 14, 1997PublishedCited by 2 opinions

1Opinion of the Court

—In a proceeding pursuant to CPLR article 75 to permanently stay arbitration, the appeal is from a judgment of the Supreme Court, Westchester County (Silverman, J.), entered February 15, 1996, which granted the petition.

Ordered that the judgment is affirmed, with costs.

In April 1991, the petitioner entered into a contract with the State of Connecticut for the construction of an office complex in Newington, Connecticut. The contract between the petitioner and the State of Connecticut contained an arbitration clause. In July 1991, the petitioner entered into a subcontract with the appellant,…

2Cases cited5 opinions

  1. Bichler v. Eli Lilly & Co.New York Court of Appeals · 1982
  2. Loughry v. Lincoln First Bank, N. A.New York Court of Appeals · 1986
  3. Parkin v. Cornell University, Inc.New York Court of Appeals · 1991
  4. Janmort Leasing, Inc. v. Econo-Car International, Inc.District Court, E.D. New York · 1979
  5. Up-Front Industries, Inc. v. U. S. Industries, Inc.New York Court of Appeals · 1984

3Cited by2 opinions

  1. Wonder Works Construction Corp. v. R.C. Dolner, Inc.Appellate Division of the Supreme Court of the State of New York · 2010
  2. National Retail Services, Inc. v. Blockbuster Videos, Inc.Appellate Division of the Supreme Court of the State of New York · 1999

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API