Land Paving Co. v. D. A. Construction Co.
Nebraska Supreme Court
1Per curiam
The issue upon this appeal is whether the plaintiff was entitled to prejudgment interest.
The action was brought to recover $8,329.68, the balance due the plaintiff on an express contract for paving a parking lot. There was no dispute about the amount due the plaintiff if the work was performed satisfactorily.
The defendant’s answer alleged the work had not been substantially performed in a good and workmanlike manner. The defendant counterclaimed for damages in the amount of $25,749.50, an amount alleged to be required to bring the work into compliance with the plans and specifications.
After…
2Cases cited3 opinions
- Langel Chevrolet-Cadillac, Inc. v. Midwest Bridge & Construction Co.Nebraska Supreme Court · 1983
- Classen v. BECTON, DICKINSON AND CO.Nebraska Supreme Court · 1983
- First Data Resources, Inc. v. Omaha Steaks International, Inc.Nebraska Supreme Court · 1981
3Cited by11 opinions
- Weyh v. GottschNebraska Supreme Court · 2019
- Fee v. FeeNebraska Supreme Court · 1986
- Troy v. RFD-TV The Theater, LLCCourt of Appeals of Tennessee · 2016
- Slusarski v. American Confinement Systems, Inc.Nebraska Supreme Court · 1984
- Circle 76 Fertilizer, Inc. v. NelsenNebraska Supreme Court · 1985
6 more not listed; retrieve them via the Exa API.