Carson v. Parks
Court of Appeals of Georgia
1Opinion of the Court
Quillian, Presiding Judge.
This appeal was taken from the verdict of a jury in an action by the plaintiff seeking to recover for work he contended he performed under a contract with the defendant to build a house. After judgment for plaintiff, defendant appeals. Held:
1. Plaintiff and defendant entered into a contract for construction of a house which stated: "purchaser shall pay contractor’s cost of all improvements plus 5% overhead and 10% profit.” Defendant gave plaintiff a $1,000 note "a couple of days before closing.” Defendant testified that he "withheld that [$1,000] to make sure that…
2Cases cited8 opinions
- McKee v. CartledgeCourt of Appeals of Georgia · 1949
- Kollen v. High Point Forest, Inc.Court of Appeals of Georgia · 1961
- Keiley v. Citizens Savings Bank & Trust Co.Supreme Court of Georgia · 1931
- Mathis-Akins Concrete Block Co. v. TuckerCourt of Appeals of Georgia · 1972
- Little v. MerckCourt of Appeals of Georgia · 1971
3 more not listed; retrieve them via the Exa API.
3Cited by3 opinions
- Cassville-White Associates, Ltd. v. Bartow Associates, Inc.Court of Appeals of Georgia · 1979
- Barylak v. JordanCourt of Appeals of Georgia · 1980
- McCormick v. ClemensonCourt of Appeals of Georgia · 1983