Office of Consumers' Counsel v. Federal Energy Regulatory Commission, Great Plains Gasification Associates, Tennessee Gas Pipeline Co., Columbia Gastransmission Corp., Transcontinental Gas Pipe Line Corp., Natural Gas Pipelineco. Of America, Madison Gas and Electric Co., Wisconsin Power and Light Co., u.s.department of Energy, Michigan Wisconsin Pipeline Co., General Motors Corp.,public Service Commission of New York, Intervenors. General Motors Corporation v. Federal Energy Regulatory Commission, Tennessee Gas Pipeline Co., Columbia Gas Transmission Corp., Transcontinentalgas Pipeline Corp., Natural Gas Pipeline Co. Of America, Madison Gas Andelectric Co., Wisconsin Power and Light Co., U. S. Department of Energy,michigan Wisconsinpipeline Co., Public Service Commission of New York, Office of Consumers'counsel of Ohio, Gas Research Institute, Great Plains Gasification Associates,intervenors. The Public Service Commission of the State of New York v. Federal Energy Regulatory Commission, Tennessee Gas Pipeline Co., Columbia Gas Transmission Corp., Transcontinentalgas Pipe Line Corp., Natural Gas Pipeline Co. Of America, Madison Gas Andelectric Co., Wisconsin Power and Light Co., U. S. Department of Energy,general Motors Corp.,michigan Wisconsin Pipeline Co., Office of Consumers' Counsel of Ohio, Gasresearch Institute, Great Plains Gasification Associates, Intervenors. The State of Michigan v. Federal Energy Regulatory Commission, Tennessee Gas Pipeline Co., Columbia Gas Transmission Corp., Transcontinentalgas Pipe Line Corp., Natural Gas Pipeline Co. Of America, Madison Gas Andelectric Co., Wisconsin Power and Light Co., U. S. Department of Energy,michigan Wisconsinpipeline Co., General Motors Corp., Public Service Commission of New York,office of Consumers' of Ohio, Gas Research Institute, Great Plains Gasificationassociates, Intervenors
Court of Appeals for the D.C. Circuit
1Opinion of the Court
655 F.2d 1132
210 U.S.App.D.C. 315, 40 P.U.R.4th 473
OFFICE OF CONSUMERS' COUNSEL, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Great Plains Gasification Associates, Tennessee Gas Pipeline
Co., Columbia GasTransmission Corp., Transcontinental Gas
Pipe Line Corp., Natural Gas PipelineCo. of America, Madison
Gas and Electric Co., Wisconsin Power and Light Co.,
U.S.Department of Energy, Michigan Wisconsin Pipeline Co.,
General Motors Corp.,Public Service Commission of New York,
Intervenors.
GENERAL MOTORS CORPORATION, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Tennessee…
2Cases cited31 opinions
- Skidmore v. Swift & Co.Supreme Court of the United States · 1944
- Securities & Exchange Commission v. Chenery Corp.Supreme Court of the United States · 1947
- Ernst & Ernst v. HochfelderSupreme Court of the United States · 1976
- Federal Power Commission v. Hope Natural Gas Co.Supreme Court of the United States · 1944
- Permian Basin Area Rate CasesSupreme Court of the United States · 1968
26 more not listed; retrieve them via the Exa API.
3Cited by1 opinion
- Natural Gas Pipeline Company of America v. Federal Energy Regulatory CommissionCourt of Appeals for the D.C. Circuit · 1985