Sherman v. Western Construction Co.
Washington Supreme Court
1Opinion of the CourtSimpson, J.
— Plaintiffs instituted this action to recover a sum of money claimed to be due on a written contract. The case, tried to the court, resulted in the entry of judgment in favor of plaintiffs. Defendant has appealed.
The assignments of error relate to actions of the court in striking certain portions of appellant’s defense and in the entry of findings of fact, conclusions of law, and judgment in favor of respondents.
The facts may be stated as follows: In November, 1937, appellant, as general contractor for the construction of a post office, agreed to pay Austin Plumbing & Heating Co.…
2Cases cited4 opinions
- Rust v. United States Fidelity & Guaranty Co.Washington Supreme Court · 1915
- W. T. Rawleigh Co. v. LangelandWashington Supreme Court · 1927
- Western Construction Co. v. AustinWashington Supreme Court · 1940
- Karr v. PeterAppellate Court of Illinois · 1895
3Cited by4 opinions
- Castro v. PeopleSupreme Court of Colorado · 1959
- National Bank v. Equity InvestorsWashington Supreme Court · 1976
- BMO Bank NA v. Raiden LLCDistrict Court, W.D. Washington · 2023
- Bernal v. The Boeing CompanyDistrict Court, W.D. Washington · 2024