Detroit Edison Co. v. Michigan Dep't of Envtl. Quality
District Court, E.D. Michigan
1Opinion of the Court
INTERIM REMEDIAL ORDER
FEIKENS, District Judge.
1. Introduction
The essential controversy of the above-styled consolidated cases is whether The Detroit Edison Company (“Edison”) violated the federal Clean Air Act (“CAA”), as well as applicable state and county law, when it chose not to obtain environmental permitting before restarting and operating its coal-fired Connors Creek Power Plant (“the Plant”), which is located in Detroit, Michigan and had been unused for almost a decade. Edison temporarily operated the Plant in 1998 in order to meet the greatly increasing energy demand of its Detroit…
2Cases cited1 opinion
- Detroit Edison Co. v. Michigan Department of Environmental QualityDistrict Court, E.D. Michigan · 1998
3Cited by2 opinions
- Bowers v. Pollution Control Hearings Bd.Court of Appeals of Washington · 2000
- Bowers v. Pollution Control Hearings BoardCourt of Appeals of Washington · 2000