Grover-Dimond Associates, Inc. v. American Arbitration Ass'n
Supreme Court of Minnesota
1Opinion of the Court
Otis, Justice.
The issue on this appeal is whether arbitration proceedings between a building owner and its contractor may be conducted jointly with an arbitration between the owner and its architect. The trial court denied the architect’s motion to prohibit joint arbitration and the architect appeals. We affirm.
These proceedings arise out of the construction of the Capital Centre Skyway Building by the owners, Eljay Partnership and Northerly Centre Corporation, in downtown St. Paul. Northerly Centre retained as architect, Grover-Dimond Associates, Inc., under a contract which contained the…
2Cases cited7 opinions
- Layne-Minnesota Co. v. Regents of the University of MinnesotaSupreme Court of Minnesota · 1963
- Atcas v. Credit Clearing Corporation of AmericaSupreme Court of Minnesota · 1972
- In re the Arbitration between Vigo Steamship Corp.New York Court of Appeals · 1970
- Columbia Broadcasting System, Inc. v. American Recording & Broadcasting Ass'nCourt of Appeals for the Second Circuit · 1969
- In re the Arbitration between Symphony Fabrics Corp. & Bernson Silk Mills, Inc.New York Court of Appeals · 1963
2 more not listed; retrieve them via the Exa API.
3Cited by45 opinions
- Keating v. Superior CourtCalifornia Supreme Court · 1982
- Illinois Farmers Insurance Co. v. Glass Service Co.Supreme Court of Minnesota · 2004
- Bel Pre Medical Center, Inc. v. Frederick Contractors, Inc.Court of Special Appeals of Maryland · 1974
- Exber, Inc. v. Sletten Construction CompanyNevada Supreme Court · 1976
- Atlas Plastering, Inc. v. Superior CourtCalifornia Court of Appeal · 1977
40 more not listed; retrieve them via the Exa API.