Lake Shore Electric Ry. Co. v. Public Utilities Commission
Ohio Supreme Court
1Opinion of the Court
By the Court.
The questions presented in this proceeding are stated by counsel for plaintiff in error as follows: First, the evidence adduced on the hearing does not establish that the public convenience and necessity require the increase of capacity applied for as to either certificate No. 407 or certificate No. 408. Second, the Public Utilities Commission, in its order overruling the application for rehearing, erroneously held that Section 614-94a, General Code, permits an increase in capacity under irregular certificate No. 408 without showing convenience and necessity.
From a consideration…
2Cited by2 opinions
- Furstenberg v. Omaha & Council Bluffs Street Railway Co.Nebraska Supreme Court · 1937
- Lake Shore Electric Ry. Co. v. Public Utilities CommissionOhio Supreme Court · 1929