Saginaw Lumber Co. v. Stirling
Michigan Supreme Court
1Opinion of the CourtSharpe, J.
This is a suit to foreclose a material-man’s statutory lien.
' In July, 1941, Neil D. Stirling and Florence M. Stirling, his wife, the owners of certain real estate, contracted will1 Prank L. Sawyer for the construction of a home. The contract price was $5,875 and was to he paid at stated periods as the work progressed. Sawyer commenced work and entered into an agreement with plaintiff lumber company for the furnishing of materials. The first materials were furnished on August 26,1941. "Within 15 days from the furnishing of the first materials, plaintiff sent by registered mail an envelope…
2Cases cited5 opinions
- Nurmi v. BeardsleyMichigan Supreme Court · 1936
- Blakeley v. MoshierMichigan Supreme Court · 1892
- Hurd v. MeyerMichigan Supreme Court · 1932
- Wyoming Park Lumber & Fuel Co. v. Vander ArkMichigan Supreme Court · 1939
- Jepherson v. TuckerSupreme Court of Rhode Island · 1893
3Cited by10 opinions
- Wallich Lumber Co. v. GoldsMichigan Supreme Court · 1965
- Lundstrom Construction Co. v. DygertSupreme Court of Minnesota · 1959
- Bukowitz v. Maryland Lumber Co.Court of Appeals of Maryland · 1956
- Burton Drywall, Inc. v. KaufmanMichigan Court of Appeals · 1976
- STURGIS SAVINGS AND LOAN ASS'N v. Italian Village, Inc.Michigan Court of Appeals · 1978