Massachusetts Appeals Court
1Opinion of the CourtLaurence, J.
In April, 1987, the Danvers water and sewer commission adopted a" Sewer Connection Permit Program (SCPP). A principal feature of the SCPP was an increase of the sewer connection fee (from a flat $10 per connection to a rate of $4 for each gallon of sewage to be discharged daily) to be paid by landowners seeking to connect to the common sewer system or to increase usage by an existing connection. The plaintiffs, trustees of the Portside Realty Trust (Port-side), paid $58,000 pursuant to the SCPP to connect seven condominium buildings they were developing to the Danvers system. Portside…
2Cases cited22 opinions
- Davis v. Boston Elevated Railway Co.Massachusetts Supreme Judicial Court · 1920
- Commonwealth v. DominicoMassachusetts Appeals Court · 1974
- Emerson College v. City of BostonMassachusetts Supreme Judicial Court · 1984
- Langlitz v. Board of Registration of ChiropractorsMassachusetts Supreme Judicial Court · 1985
- Greenleaf v. Massachusetts Bay Transportation AuthorityMassachusetts Appeals Court · 1986
17 more not listed; retrieve them via the Exa API.
3Cited by16 opinions
- Nuclear Metals, Inc. v. Low-Level Radioactive Waste Management BoardMassachusetts Supreme Judicial Court · 1995
- Dragon v. Vanguard Industries, Inc.Supreme Court of Kansas · 2006
- Dupont v. Town of DracutMassachusetts Appeals Court · 1996
- Morton v. Town of HanoverMassachusetts Appeals Court · 1997
- Silva v. City of AttleboroMassachusetts Supreme Judicial Court · 2009
11 more not listed; retrieve them via the Exa API.