Kentucky Metal Products Co. v. United States
United States Court of Claims
1Opinion of the Court
*779 Opinion
per Ouriam:
The amount of increased cost for material claimed in this suit is $1,286.84 for the ten subcontracts ; the claimed increased costs on the Billings, Mont., and Jonesboro, Ark., subcontracts are $12.46 and $2.87, respectively. No increased costs prior to August 10, 1933, are claimed.
On the evidence submitted plaintiff has not shown what amount of increased cost, if any, was incurred for material as a result of enactment of the National Industrial Kecovery Act.
On the two subcontracts and the eight sub-subcontracts mentioned in the findings plaintiff incurred increased labor…
2Cases cited1 opinion
- John B. Kelly, Inc. v. United StatesUnited States Court of Claims · 1938