On May 23, 1921, the plaintiffs, Irwin and Leighton, made a preliminary contract with the defendant, Jacob Weikel, for the construction of an addition to his hotel, the Shelburne, at Atlantic City, for $650,000; to be followed by a formal contract which was prepared and duly executed on June 8th of the same year. The latter recited, inter alia, that a corporation to be known as “The Shelburne Inc.” was in process of formation to whom Weikel, who was to be sole stockholder, was to convey the hotel property, and which corporation he guaranteed would, not later than…
2Cases cited12 opinions
- Rhodes v. TerheydenSupreme Court of Pennsylvania · 1922
- Buehler v. United States Fashion Plate Co.Supreme Court of Pennsylvania · 1921
- King Et Al., Appellants, v. BrillhartSupreme Court of Pennsylvania · 1921
- Parry v. First National BankSupreme Court of Pennsylvania · 1921
- Franklin Sugar Refining Co. v. Lykens Mercantile Co.Supreme Court of Pennsylvania · 1922
7 more not listed; retrieve them via the Exa API.
3Cited by16 opinions
- Smith v. LenchnerSuperior Court of Pennsylvania · 1964
- National Cash Register Co. v. AnsellSuperior Court of Pennsylvania · 1936
- Tri-State Roofing Co. v. SimonSuperior Court of Pennsylvania · 1958
- Palatucci v. WoodlandSuperior Court of Pennsylvania · 1949
- Pziepoira v. LongSupreme Court of Pennsylvania · 1940
11 more not listed; retrieve them via the Exa API.