1Opinion of the Court
— Cross appeal unanimously dismissed without costs and otherwise order affirmed. Memorandum: The parties entered into a contract for asbestos removal work to be performed by plaintiff at defendant’s elementary schools. On August 2, 1988, 11 days before plaintiff’s work was to have been completed under the contract, a fire occurred in the gymnasium at the Gorham Elementary School. Plaintiff cleaned up and repaired the fire damage before completing its asbestos removal work. When defendant rejected plaintiff’s claims for payment of expenses incurred in repairing the fire *1019damage and the…
2Cases cited2 opinions
- Town of Massena v. Niagara Mohawk Power Corp.New York Court of Appeals · 1978
- Mareno v. University of the State of New York Agricultural & Technical CollegeAppellate Division of the Supreme Court of the State of New York · 1984
3Cited by3 opinions
- Damstetter v. MartinAppellate Division of the Supreme Court of the State of New York · 1998
- Flower City Insulation Sales & Contractors, Inc. v. Board of EducationAppellate Division of the Supreme Court of the State of New York · 1993
- Flower City Insulation Sales & Contractors, Inc. v. Board of Education—Marcus Whitman Central School DistrictAppellate Division of the Supreme Court of the State of New York · 1995