Mallory v. Daniel Lumber Co.
Court of Appeals of Georgia
1Opinion of the Court
Banke, Presiding Judge.
The appellee contracted to build a commercial office building for the appellant for a base price of approximately $644,000. The con tract specified that “[a]ll changes in price will become a part of the contract when both parties have signed their acceptance.” After the appellant had made progress payments totalling approximately $521,000, a dispute arose between the parties over how much remained to be paid for the work which had thus far been performed on the project. As a result of this dispute, the appellant refused to make additional progress payments, and the…
2Cases cited7 opinions
- Polito v. HollandSupreme Court of Georgia · 1988
- Maloy v. DixonCourt of Appeals of Georgia · 1972
- Jordan Bridge Co. v. I. S. Bailey, Jr., Inc.Court of Appeals of Georgia · 1982
- Bayliner Marine Corp. v. PranceCourt of Appeals of Georgia · 1981
- Knight v. Atlanta Transit Sys., Inc.Court of Appeals of Georgia · 1976
2 more not listed; retrieve them via the Exa API.
3Cited by6 opinions
- Amalgamated Transit Union Local 1324 v. RobertsSupreme Court of Georgia · 1993
- Beall v. F. H. H. Construction, Inc.Court of Appeals of Georgia · 1989
- Fine & Block v. EvansCourt of Appeals of Georgia · 1991
- U. S. Industries, Inc. v. AustinCourt of Appeals of Georgia · 1990
- Citizens & Southern Trust Co. v. HicksCourt of Appeals of Georgia · 1995
1 more not listed; retrieve them via the Exa API.