Ilg Electric Ventilating Co. v. Conner

Supreme Court of Minnesota

Decided October 21, 1927No. 26,260PublishedCited by 9 opinions

1Opinion of the CourtHolt, J.

Suit upon a public contractor’s bond for materials, ventilating fans, furnished by plaintiff to the contractors in the erection by them of the Michael Dowling School in Minneapolis. The court found that plaintiff failed to serve the notice required by law in order to maintain the action and directed judgment in favor of the bonding company. The appeal is from the order denying a new trial.

The only question presented is whether a sufficient notice was served on the company. The testimony was that the same sort of notice was served in the same manner on the contractors.

Section 9705, G. S. 1923,…

2Cases cited4 opinions

  1. State ex rel. Patterson v. BatesSupreme Court of Minnesota · 1905
  2. Paxton & Hershey Irrigating Canal & Land Co. v. Farmers & Merchants Irrigation & Land Co.Nebraska Supreme Court · 1895
  3. Leavitt v. LoveringSupreme Court of New Hampshire · 1888
  4. James B. Clow & Sons v. A. W. Scott Co.Supreme Court of Minnesota · 1925

3Cited by9 opinions

  1. Pressman v. State Tax CommissionCourt of Appeals of Maryland · 1985
  2. Bull v. KingSupreme Court of Minnesota · 1939
  3. Ceco Steel Products Corp. v. TapagerSupreme Court of Minnesota · 1940
  4. Wheeler Lumber Bridge & Supply Co. v. Seaboard Surety Co.Supreme Court of Minnesota · 1944
  5. Silver v. Fidelity & Deposit Co. of MarylandNew Mexico Supreme Court · 1935

4 more not listed; retrieve them via the Exa API.

Showing a preview — retrieve the full document via the Exa API.

Powered by the Exa API